Subpart 1. Submittal documents.
Construction documents, special inspection and structural observation programs, and other data shall be submitted in one or more sets with each application for a permit.
Exception: The building official may waive the submission of construction documents and other data if the nature of the work applied for is such that reviewing of construction documents is not necessary to obtain compliance with the code.
The building officer may require plans or other data be prepared according to the rules of the Board of Architecture, Engineering, Land Surveying, Landscape Architecture, Geoscience and Interior Design, chapter 1800, and Minnesota Statutes, sections 326.02 to 326.15, and other state laws relating to plan and specification preparation by occupational licenses. If special conditions exist, the building official may require additional construction documents to be prepared by a licensed design professional.

Subp. 2. Information on construction documents.
Construction documents shall be dimensioned and drawn upon suitable material. Electronic media documents are permitted to be submitted when approved by the building official. Construction documents shall be of sufficient clarity to indicate the location, nature, and extent of the work proposed and show in detail that it will conform to the code and relevant laws, ordinances, rules, and regulations, as determined by the building official.

Subp. 3. Manufacturer's installation instructions.
When required by the building official, manufacturer's installation instructions for construction equipment and components regulated by the code, shall be available on the job site at the time of inspection.

Subp. 4. Site plan.
The construction documents submitted with the application for permit shall be accompanied by a site plan drawn to scale, showing the size and location of new construction and existing structures on the site, distances from lot lines, the established street grades, and the proposed finished grades, and it shall be drawn according to an accurate boundary line survey. In the case of demolition, the site plan shall show construction to be demolished and the location and size of existing structures and construction that are to remain on the site or plot. The building official may waive or modify the requirement for a site plan if the application for permit is for alteration or repair or when otherwise warranted.

Subp. 5. Examination of documents.
The building official shall examine or cause to be examined the accompanying construction documents to ascertain whether the construction indicated and described complies with the requirements of the code and other pertinent laws and ordinances.

Subp. 6. Approval of construction documents.
A. If the building official issues a permit, the construction documents shall be approved in writing or by a stamp, stating "Reviewed for Code Compliance," dated, and signed by the building official or an authorized representative. One set of the construction documents that were reviewed shall be retained by the building official. The other set shall be returned to the applicant, kept at the site of the work, and open to inspection by the building official or an authorized representative.
B. Any code deficiencies identified by the building official during the plan review process for construction documents that are prepared by a design professional who is licensed or certified under Minnesota Statutes, sections 326.02 to 326.15, must be itemized by the building official through a comprehensive plan review letter only. Any code deficiencies identified by the building official during the plan review process for construction documents that are not prepared by a licensed or certified design professional may be marked directly on the document or itemized by the building official through a comprehensive plan review letter. The issuance of a permit based on construction documents and other data does not prevent the building official from requiring the correction of errors in the construction documents and other data. All sets of required construction documents, including the site copy, municipality copy, or inspector copy, must be marked identically by the building official, with one copy retained by the building official after construction is completed. Work regulated by the code must be installed according to the reviewed construction documents. Work that does not comply with approved construction documents must not proceed until the applicant submits changes that are approved by the building official.

Subp. 7. Previous approvals.
The code in effect at the time of application shall be applicable.

Subp. 8. Phased approval.
The building official may issue a permit for the construction of foundations or any other part of a building or structure before the construction documents for the whole building or structure have been submitted, provided that adequate information and detailed statements have been filed complying with pertinent requirements of the code. The holder of the permit for the foundation or other parts of a building or structure shall proceed at the holder's own risk with the building operation and without assurance that a permit for the entire structure will be granted.

Subp. 9. Design professional in responsible charge.
A. The building official may require the owner to engage and designate on the building permit application a licensed design professional who shall act as the licensed design professional in responsible charge. If the circumstances require, the owner shall designate a substitute licensed design professional in responsible charge who shall perform the duties required of the original licensed design professional in responsible charge. The building official shall be notified in writing by the owner if the licensed design professional in responsible charge is changed or is unable to continue to perform the duties. The licensed design professional in responsible charge shall be responsible for reviewing and coordinating submittal documents prepared by others, including phased and deferred submittal items, for compatibility with the design of the building. When structural observation is required by the code, the inspection program shall name the individual or firms who are to perform structural observation and describe the stages of construction at which structural observation is to occur.
B. For the purposes of this part, deferred submittals are defined as those portions of the design that are not submitted at the time of the application and that are to be submitted to the building official within a specified period. Deferral of any submittal items shall have the prior approval of the building official. The licensed design professional in responsible charge shall list the deferred submittals on the construction documents for review by the building official. Submittal documents for deferred submittal items shall be submitted to the licensed design professional in responsible charge who shall review them and forward them to the building official with a notation indicating that the deferred submittal documents have been reviewed and that they have been found to be in general conformance with the design of the building. The deferred submittal items shall not be installed until their design and submittal documents have been approved by the building official.
C. Work regulated by the code shall be installed according to the reviewed construction documents, and any changes made during construction that are not in compliance with the approved construction documents shall be resubmitted for approval as an amended set of construction documents.
Source: Legislative text reproduced verbatim
Plain English

Minn. R. 1300 § 1300.0130 establishes the rules governing construction documents that must accompany permit applications in Minnesota. Applicants are generally required to submit dimensioned, detailed plans—along with site plans and any special inspection programs—sufficient to show that proposed work will comply with the building code and applicable laws. The building official reviews these documents, may approve them with a compliance stamp, and retains a copy; work must follow the approved documents, and any deviations require resubmission and re-approval before proceeding.

Written by anthropic/claude-sonnet-4.6 · Reviewed on September 30, 2026

Plain English — not legal advice.

For Property Managers

Under Minn. R. 1300 § 1300.0130, property owners and managers pursuing construction or renovation projects typically ensure that complete, dimensioned construction documents and a scaled site plan are submitted with every permit application. Compliant operators keep the building-official-approved set on the job site and open to inspection at all times, and they submit amended documents for any changes that arise during construction rather than proceeding with unapproved deviations. When a licensed design professional is designated as the professional in responsible charge, owners generally notify the building official in writing of any change to that individual and ensure deferred submittal items receive approval before installation begins.

General guidance for property managers — not legal advice for your specific situation. Consult an attorney for advice on your case.

For Tenants

Minn. R. 1300 § 1300.0130 is relevant to tenants when construction or renovation work is being performed on a property they occupy, because it requires that all such work follow building-official-approved construction documents. If work appears to be proceeding without a posted approved plan set or in a manner inconsistent with what was approved, tenants may contact the local building department to inquire about permit and document status. Tenant-rights organizations and legal aid services can help tenants understand how building code compliance under this provision may intersect with habitability rights or other protections.

General guidance for tenants — not legal advice for your specific situation. Consult a tenant-rights organization or attorney for advice on your case.

Generated September 30, 2026 — auto-generated, not yet human-reviewed. See /transparency for methodology.

Effective Timeline

Current
Sep 30, 2026
Click on timeline segments to view historical versions.

References Out

No outbound references recorded yet for this provision.

References In

No inbound references recorded yet for this provision.

Related Rules

§ 14.544
LICENSE REQUIREMENTS
§ 14.545
STANDARDS FOR HEALTH, SAFETY AND NUISANCE PREVENTION
§ 14.546
SANCTIONS AND PENALTIES

Source Information

Snapshot SHA:
Fetched:Sep 30, 2026, 01:24 PM UTC